Software Project Scheduling (8)[detail]

Show Answer
Calendar
Simplest form of scheduling
key factors for scheduling
(i) Activities, (ii) milestones, (iii) start and end date of project, (iv) concurrent activities required, (v) sequential activities required, (vi) the presence or potential for resources conflicts, (vii) resource limitations.
3 point cost effort estimation
real/optimistic/pessimistic estimates
Earned value
difference between scheduled completion and actual completion
parametric estimation
estimate using a project variable e.g. lines of code for cost, budget, or duration
analogous estimation
estimate based on historical data from a similar project or activity
schedule variance
difference of earned value and planned value
cost variiance
difference of earned value and actual cost